Provisional conditioning was made with asphalt emulsion of slow breaking and with sand, of the existing road to grant more stability to the ground and to achieve provisionally the vehicular traffic to gain access to the project. The work was done for our client Constructora Buenavista, the project was located in the west of the city, in Santa Teresita.
At the same time, the demolition of the existing folder, the removal of the certified filling material, the shaping of the subgrade and the base leveling were developed, since in some sectors it was necessary to supply material of this type. .
We supplied, extended and compacted asphalt mix MDC-2, to finally leave the rolling folder with a thickness of 3".